Apartment Finishing Stages in Egypt: The Right Order, Step by Step (2026)

The correct order of apartment finishing works in Egypt, from design and BOQ through plumbing, electrical, plaster, waterproofing, tiling, gypsum board, paint, carpentry and handover — and what to check at each stage.

Large-format porcelain being laid with levelling clips in a Rehab apartment by Cylesta Interiors

Most finishing problems in Egyptian apartments come from doing things in the wrong order: tiling before the kitchen is designed, closing walls before pipes are tested, or painting before the gypsum board is finished. Here is the order we follow, and what to check at each step.

1. Design, BOQ and approvals

Start with the interior design and working drawings, then a written BOQ with items, quantities and named materials. In a compound, get the management approvals before any work starts. Decide the kitchen layout, bathroom fixtures and AC system now, because they set where every connection goes.

2. Demolition and rough-in

  • Demolition and any wall changes from the design.
  • Plumbing supply and drainage, pressure-tested before walls are closed.
  • Electrical conduits, boxes and the distribution board, following the lighting and socket layout.
  • AC copper piping and drain lines, and ventilation for kitchen and bathrooms.

3. Plaster and screed

Walls are plastered and floors are screeded to the right levels. Check that walls are straight and corners square — every later finish depends on it.

4. Waterproofing wet areas

Bathrooms, kitchens and balconies are waterproofed, then flood-tested before tiles go down. Any leak found now costs little to fix; found after handover it means breaking finished tiles.

5. Tiling and stone

Floors and wall tiles are laid with agreed starting points so cut tiles sit where they are least visible. Check levels, joints and hollow-sounding tiles. Read more in our guide to finishing levels.

6. Gypsum board and ceilings

False ceilings, concealed lighting coves and decorative gypsum work are built, with access panels for AC units and valves.

7. Paint

Putty and primer coats, then final paint after the dusty works are finished. The paint type, brand and number of coats should be in the BOQ.

8. Carpentry, kitchen and fixtures

Doors, wardrobes and the kitchen are measured on site after tiling and paint, then installed. Sanitary fixtures, switches, sockets and light fittings go in last.

9. Snag list and handover

Walk through every room with a snag list, fix what is open, clean, and hand over with the warranty in writing. At Cylesta every project carries a one-year workmanship warranty.

Frequently asked questions

What is the first step in finishing an apartment?

Design and a written BOQ. They decide where every pipe, socket and fixture goes, so rough-in works are done right the first time.

When should waterproofing be done?

After plaster and screed in wet areas, and it should be flood-tested before tiling starts.

When are the kitchen and wardrobes measured?

On site after tiling and paint, so the sizes are exact.

How long does apartment finishing take?

Typically 4–6 months at Cylesta, depending on size, unit condition, finishing tier and compound approvals.